In the Quay Commander window, you can use the Actions drop-down list to rearrange the work queue schedule and manage crane shifts and the overall crane plan, as described in the following table. Which options in this list are available at a time depends on whether you have selected a work queue block or a crane shift block. Regardless of your selection, you can always:
Adjust shifts to match a vessel visit
Select all shifts
Adjust the crane scheduler rate
Save the crane plan state
Load the crane plan state
Open a crane activities list
Option |
Description |
Available For |
---|---|---|
Dual Cycle selected queues |
Dual-cycles the selected discharge and load work queues (WQ) for a bay. See also Link work queues for dual cycling (on page 1). |
Work queue |
Cancel Dual Cycle |
Cancels the dual cycle for the selected WQs. Before canceling the dual cycle, make sure the selected WQs are deactivated and all dispatched WIs are system-bypassed. |
Work queue |
Link Selected shifts |
Links the selected shifts (on page 1) to handle shift overruns. |
Crane shift |
Unlink selected shifts |
Unlink the selected shifts (on page 1) |
Crane shift |
Unlink selected queues from their POWs |
Unlinks or unassigns selected work-queue blocks from their crane or points of work (POW). See also Unassign work queues (on page 1) and Identify a shift overrun (on page 1). |
Work queue |
Create Activity for Selected Shift |
Opens the Edit Shift Activity dialog box, where you can create an activity for the selected shift. |
Crane shift |
Create Activity for Selected Queues |
Adds a crane activity, such as a break-bulk move or hatch lift, to selected work-queue blocks. See also Add shift activities (on page 1). |
Work queue |
Split Selected Queue |
Hard-splits a selected work queue, such as when you need to equalize the workload among two or more cranes. See also Split work queues (on page 1). |
Work queue |
Modify Queue |
Lets you enter queue notes, which print in the Shift Work Letter and Shift Productivity Report. |
Work queue |
Set Queue Productivity |
Opens the Queue Productivity dialog box, which enables you to view or set productivity for the selected work queue. Typically, the Use Shift Productivity check box is selected and you use productivity already set for the shift. When you clear the check box, you can modify the productivity for the crane shift. |
Work queue |
Adjust Shifts to Match Visit |
Synchronizes all shifts for a vessel visit. The shifts get moved as a group to be in alignment with the start of the vessel visit. This is especially helpful for adjusting a crane plan for early or late arriving vessels. See also Handling vessel schedule changes (on page 1). |
Work queue Crane shift |
Select All Shifts |
Selects all work shifts. |
Work queue Crane shift |
Crane scheduler rate |
Specifies the frequency of crane plan updates. This is an important consideration because scheduling uses a large amount of system resources. You can choose one of the following update frequencies:
You can also specify the crane scheduler rate using the XPS setting CRSHRT. The value you select here overrides the value specified in CRSHRT. |
Work queue Crane shift |
Save Crane Plan State |
Saves the current state of the crane plan |
Work queue Crane shift |
Load Crane Plan State |
Reloads the saved crane plan state |
Work queue Crane shift |
Crane Activities List |
Opens the Crane Activities window |
Work queue Crane shift |
Start selected shift working |
Time-stamps the beginning of the selected shift. If you do not use this option, XPS uses the start time as defined for the shift. This option is useful if the ship is late and you would like accurate productivity data. |
Crane shift |
Finish selected shift |
Time-stamps the completion of the selected shift. If you do not use this option, XPS uses the shift end time. This item is useful if the shift finishes early and you would like accurate productivity data. |
Crane shift |
Suspend selected shift |
Time-stamps a break in the work of a shift. This option is useful for accurate productivity data. |
Crane shift |